A pre-arrival meeting is scheduled two days before the estimated time of arrival of the cargo vessel, to be attended by the ship agent. The purpose of the meeting is to plan the berthing of the vessel and the operational procedures during loading/unloading of cargoes.


Berths

PIER / WHARF / QUAY LENGTH (m) DEPTH(m)
Alava Wharf (Waterfront) 520 12
Alava Extension (Waterfront) 181 15
Bravo Wharf (SRF) 411 7.5
Rivera Wharf-West 149.7 7
Rivera Wharf-South 126.6 13
Rivera Wharf-East 335.3 10
Rivera Wharf-North 294.4 9
Boton Wharf (Cubi Point) 648.3 9
Sattler Pier (NSD) 180 12
Marine Terminal 225 12
Pol Pier (Cubi Point) 253 10
Leyte Pier (Cubi Point) 300 15
Nabasan Wharf (NavMag) 180 14
Camayan Wharf (NavMag) 135 10
C-Quav (Subic Shipyard) 300 9
E-1 Quay (Subic Shipyard) 255 9
E-2 Quay (Subic Shipyard) 205 9

The main commercial port will be at the Sattler Pier and Marine Terminal Pier located at the former NSD Compound. The other piers in the area will complement and support the main commercial port.


Containers

Sattler Pier Lot Area - 180m (length) / 24.40m (width)
Draft - Eastside = 12m / Westside = 12m
Covered Pier
(Marine Terminal)
Lot Area - 225m (length) / 70m (width)
Draft - Eastside = 12m / Westside = 12m
Transit Shed - (L=182.93m / W=45.31m)
Area 8288.56 sqm
Freight Workload 11,636 teu's per month
(approx. with the operation of the gantry crane)
139,632 teu's per year
(approx. with the operation of the gantry crane)
Container Marshalling Yard Area - 20,903 sqm (approx.)
Storage Compound 42 hectares (approx.)
Covered Storage Area 70,550 sqm
Available Open Storage Area 164,000 sqm (approx.)